Welding Techniques and Key Process Points for Butt-Weld Flanges
Aug 19, 2025| As a critical component in pipeline connections, the quality of the weld directly impacts the system's sealing, pressure resistance, and service life. Mastering correct welding techniques is crucial for ensuring flange connection reliability.
1. Pre-Welding Preparation
Before welding, the weld surfaces of the flange and pipe must be thoroughly cleaned to remove oil, rust, and oxide layers, ensuring a clean metal surface. Also, check that the flange and pipe specifications match, especially the groove angle (typically 30°-35°) and gap (2-3mm). Excessive deviation can lead to stress concentration or incomplete weld penetration. Additionally, select low-hydrogen electrodes (such as E4315 or E5015) that match the base material and pre-dry the electrodes (bake at 350°C for one hour) to reduce the risk of hydrogen-induced cracking.
2. Welding Process Control
Use a multi-pass, multi-pass welding method. When welding the first root layer, the current should be kept low (recommended to be 10%-15% lower than the standard value). Use gentle oscillations of the welding torch to ensure complete weld penetration at the root and a slag-free weld. The current should be gradually increased during the subsequent filler layer, but overheating should be avoided to prevent flange deformation. For cap welding, focus on aesthetically pleasing finishes, control the weld pool temperature, and prevent undercutting or weld overhangs. The recommended welding sequence is to start on opposite sides of the flange and weld symmetrically to balance stresses.
3. Post-processing and Inspection
After welding, allow the weld to cool naturally to room temperature. Forced cooling is prohibited to prevent embrittlement. Use an angle grinder to clean spatter from the weld surface and conduct a 100% visual inspection to ensure the absence of defects such as pores and cracks. Internal quality testing may be performed using X-ray or ultrasonic testing if necessary. Pressure vessel flanges also require hydrostatic testing according to standards.
4. Addressing Common Problems
If lack of fusion occurs, adjust the current or optimize the groove. If the weld undercuts, reduce the arc length and control the arc amplitude. Preheating high-alloy flanges to 100-150°C and slow cooling is recommended to prevent cold cracking.
Welding butt-weld flanges requires not only technical expertise but also meticulous attention to detail. Only by strictly following the process specifications can safe and efficient pipeline system connections be achieved.